Uploaded image for project: 'OBSOLETE DM Long-range Planning OBSOLETE'
  1. OBSOLETE DM Long-range Planning OBSOLETE
  2. DLP-530

DMTC-0100-2600 Base - Archive Network Functional 1 Gbps

    Details

    • Type: Milestone
    • Status: Resolved
    • Priority: Major
    • Resolution: Done
    • Affects Version/s: None
    • Fix Version/s: S15
    • Component/s: Planning
    • Labels:
    • Milestone Level:
      2

      Description

      This is implemented as shared access on a 10 Gbps link provided by to AURA by REUNA and AmPath, LSST contributes partial funding for this link.

        Attachments

          Activity

          Hide
          jkantor Jeff Kantor added a comment -

          The prior R&D level of funding of $50k/year for this shared access will be continued in MREFC and is budgeted. There is a remaining detail to define the internal AURA mechanism to transfer the funds from the LSST to the appropriate AURA account.

          Show
          jkantor Jeff Kantor added a comment - The prior R&D level of funding of $50k/year for this shared access will be continued in MREFC and is budgeted. There is a remaining detail to define the internal AURA mechanism to transfer the funds from the LSST to the appropriate AURA account.

            People

            • Assignee:
              jkantor Jeff Kantor
              Reporter:
              klong Kevin Long
              Watchers:
              Jeff Kantor, Kevin Long
            • Votes:
              0 Vote for this issue
              Watchers:
              2 Start watching this issue

              Dates

              • Created:
                Updated:
                Resolved: