        Work is in progress on this ICD. A change request was filed by bemmons on 2016-10-19, LCR-795. Several rounds of updates to the proposed changes to LSE-131 have been discussed.

        Most recently, there was a meeting between DM and EPO on this subject on 2017-06-02. Notes from that meeting are available here: https://docs.google.com/document/d/12uhTMvfttIVpRGOpTR081WGslfQF0x4RSjRr5lc_J0k/edit?usp=sharing

        gpdf Gregory Dubois-Felsmann added a comment - Work is in progress on this ICD. A change request was filed by bemmons on 2016-10-19, LCR-795 . Several rounds of updates to the proposed changes to LSE-131 have been discussed. Most recently, there was a meeting between DM and EPO on this subject on 2017-06-02. Notes from that meeting are available here: https://docs.google.com/document/d/12uhTMvfttIVpRGOpTR081WGslfQF0x4RSjRr5lc_J0k/edit?usp=sharing

        FYI, in Primavera the EPO milestone date for "LSE-131 Phase 3 ICD Completion" is September 17, 2020 but the DM milestone date for "LSE-131 EPO-DM interface - Phase 3" is July 3, 2017. There is consensus that the EPO date is too far out (and obviously the DM date has been overtaken). womullan or gpdf or ktl any recommendations for a better target date after reviewing https://confluence.lsstcorp.org/display/SYSENG/LSE-131+Task+List+to+Achieve+P3+Completion?src=jira ?

        bemmons Ben Emmons [X] (Inactive) added a comment - FYI, in Primavera the EPO milestone date for "LSE-131 Phase 3 ICD Completion" is September 17, 2020 but the DM milestone date for "LSE-131 EPO-DM interface - Phase 3" is July 3, 2017. There is consensus that the EPO date is too far out (and obviously the DM date has been overtaken). womullan or gpdf or ktl any recommendations for a better target date after reviewing https://confluence.lsstcorp.org/display/SYSENG/LSE-131+Task+List+to+Achieve+P3+Completion?src=jira ?

        FYI, swinbank pointed me to the DM ETC 7-9-2017 (DM re-plan) sandbox which lists DLP-539 as May 10, 2017 (also overtaken).

        bemmons Ben Emmons [X] (Inactive) added a comment - FYI, swinbank pointed me to the DM ETC 7-9-2017 (DM re-plan) sandbox which lists DLP-539 as May 10, 2017 (also overtaken).

        One of our missed milestones – we will be looking st all of these probably this week - certainly soon.

        womullan Wil O'Mullane added a comment - One of our missed milestones – we will be looking st all of these probably this week - certainly soon.

        After attending the ICD Phase 3 meeting this week hosted by bselvy and kwesson and later discussing this particular milestone with womullan, we propose updating the DLP-539 and EPOC310 milestone date to August 31, 2018. Any objections?

        bemmons Ben Emmons [X] (Inactive) added a comment - After attending the ICD Phase 3 meeting this week hosted by bselvy and kwesson and later discussing this particular milestone with womullan , we propose updating the DLP-539 and EPOC310 milestone date to August 31, 2018. Any objections?

        Close 9 obsolete planning issues. The underlying work is in general complete or, if not, reflected by work otherwise documented.

        gpdf Gregory Dubois-Felsmann added a comment - Close 9 obsolete planning issues. The underlying work is in general complete or, if not, reflected by work otherwise documented.

        People

          gpdf Gregory Dubois-Felsmann
          klong Kevin Long
          Ben Emmons [X] (Inactive), Gregory Dubois-Felsmann, Kevin Long, Wil O'Mullane
          Votes:
          0 Vote for this issue
          Watchers:
          4 Start watching this issue

          Dates

            Created:
            Updated:
            Resolved:

            Jenkins

              No builds found.