Uploaded image for project: 'Data Management'
  1. Data Management
  2. DM-10296

Address unresolved issues found in building the AP prototype pipeline

    Details

    • Templates:
    • Epic Name:
      AP_Prototype_Cleanup
    • Story Points:
      50
    • WBS:
      02C.03.00
    • Team:
      Alert Production
    • Cycle:
      Fall 2017

      Description

      There will be some work to do to fix up the prototype alert production system after the initial implementation is finished. This will likely include improving ISR by adding steps or refining others, improving the way the obs packages do the bookkeeping, and wrangling data outputs.

        Attachments

          Issue Links

          Stories in Epic (Custom Issue Matrix)

          Key Summary Story Points Assignee Status
           
          DM-10298

          Unmasked "Tape Bump"

          6 Meredith Rawls Done
           
          DM-10297

          Fix "double treerings"

          6 Meredith Rawls Done

            Activity

              People

              • Assignee:
                mrawls Meredith Rawls
                Reporter:
                krughoff Simon Krughoff
                Watchers:
                John Swinbank, Simon Krughoff
              • Votes:
                0 Vote for this issue
                Watchers:
                2 Start watching this issue

                Dates

                • Created:
                  Updated:
                  Resolved:

                  Summary Panel