Uploaded image for project: 'Data Management'
  1. Data Management
  2. DM-10700

Batch Processing System Phase 1b (Pegasus)

    XMLWordPrintable

    Details

    • Epic Name:
      Batch Processing System Phase 1b
    • Story Points:
      81
    • WBS:
      02C.07.01
    • Team:
      Data Facility
    • Cycle:
      Fall 2017

      Description

      Summary: Design and begin implementing data staging, generic pegasus running with DES frontend, etc.

        Attachments

        Stories in Epic (Custom Issue Matrix)

          Activity

          Hide
          tjenness Tim Jenness added a comment -

          Was the design written down?

          Show
          tjenness Tim Jenness added a comment - Was the design written down?

            People

            Assignee:
            kooper Rob Kooper [X] (Inactive)
            Reporter:
            plutchak Joel Plutchak (Inactive)
            Watchers:
            Joel Plutchak (Inactive), Mikolaj Kowalik, Tim Jenness
            Votes:
            0 Vote for this issue
            Watchers:
            3 Start watching this issue

              Dates

              Created:
              Updated:
              Resolved:
              Start date:
              End date:

                Jenkins

                No builds found.