Batch Production Development (F17b)

    Details

    • Epic Name:
      Batch Production Development (F17b)
    • Story Points:
      55
    • WBS:
      02C.07.01
    • Team:
      Data Facility
    • Cycle:
      Fall 2017

      Description

      Interim (bucket) epic to hold September work in Batch Production to support milestone LDM-503-2

        Attachments

          Activity

          Hide
          plutchak Joel Plutchak (Inactive) added a comment -

          Planned work has been completed for this bucket epic, consisting of preparation for running test and performing work to meet milestone LDM-503-2.

          Show
          plutchak Joel Plutchak (Inactive) added a comment - Planned work has been completed for this bucket epic, consisting of preparation for running test and performing work to meet milestone LDM-503-2.

            People

            • Assignee:
              kooper Rob Kooper
              Reporter:
              plutchak Joel Plutchak (Inactive)
              Watchers:
              Joel Plutchak (Inactive)
            • Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

              Dates

              • Created:
                Updated:
                Resolved:
                Start date:
                End date:

                Summary Panel