Uploaded image for project: 'Data Management'
  1. Data Management
  2. DM-17330

Review Pointing Component v0.2 Release

    XMLWordPrintable

    Details

      Description

      This task covers the time spent to review the test results for the v0.2 Release of the Pointing Component.

        Attachments

          Activity

          Hide
          rbovill Rob Bovill added a comment -

          My review findings are in the attached document.  I focused on the Robot-Framework testing only.  I don't understand one test and want to meet with the vendor to discuss.  One test failed, but the vendor did not provide enough data to analyze, so we'll need that data.  They did not run one test, and did not provide any explanation.  However, it is my conclusion that the testing did prove they implemented the functionality we needed and that it sufficiently works.

          Show
          rbovill Rob Bovill added a comment - My review findings are in the attached document.  I focused on the Robot-Framework testing only.  I don't understand one test and want to meet with the vendor to discuss.  One test failed, but the vendor did not provide enough data to analyze, so we'll need that data.  They did not run one test, and did not provide any explanation.  However, it is my conclusion that the testing did prove they implemented the functionality we needed and that it sufficiently works.
          Hide
          rbovill Rob Bovill added a comment -

          I do want to clean up my report a bit, but I'm about to go on vacation and I wanted to get this task processed before that.  As there is more review work pending from others, I can clean up my findings later.

          Show
          rbovill Rob Bovill added a comment - I do want to clean up my report a bit, but I'm about to go on vacation and I wanted to get this task processed before that.  As there is more review work pending from others, I can clean up my findings later.
          Hide
          plotz Paul Lotz [X] (Inactive) added a comment -

          Task complete. Requires follow-up with vendor.

          Show
          plotz Paul Lotz [X] (Inactive) added a comment - Task complete. Requires follow-up with vendor.
          Hide
          rbovill Rob Bovill added a comment -

          Met with the team to discuss the release and my questions from my review.  The OSL team needs a day to get materials and data together.  There is a follow up meeting scheduled to go over that.  But this does not affect the decision to accept this release, so this review, and this task, are complete.

          Show
          rbovill Rob Bovill added a comment - Met with the team to discuss the release and my questions from my review.  The OSL team needs a day to get materials and data together.  There is a follow up meeting scheduled to go over that.  But this does not affect the decision to accept this release, so this review, and this task, are complete.

            People

            Assignee:
            rbovill Rob Bovill
            Reporter:
            rbovill Rob Bovill
            Reviewers:
            Paul Lotz [X] (Inactive)
            Watchers:
            Paul Lotz [X] (Inactive), Rob Bovill
            Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

              Dates

              Created:
              Updated:
              Resolved:
              Start date:
              End date:

                Jenkins

                No builds found.