Epic Name:Auxtel Calibration System Integration Tests in Chile
-
Story Points:15
-
WBS:1.04C.15.9 (AIV)
-
Team:Telescope and Site
Description
Milestone Epic
Location:
- Chile
Purpose:
- Auxtel Calibration System Integration Tests
Required Components:
- ATMonochromator
- FiberSpectrograph
- Electrometer
- ATSpectrograph
- ATCamera
Resources Required:
- Summit Computers & Network
- SAL
- EFD
- Calibration Scripts
Corresponds to P6 Activity:
- T&SC-6800-1462 AT Spectrograph Instrument+Detector On Telescope Testing in Chile
Attachments
Issue Links
- has to be done after
-
DM-18411 Auxtel Calibration System Integration Tests in Tucson
- Done
Key | Summary | Story Points | Assignee | Status | |
---|---|---|---|---|---|
|
|
0 | Andy Clements | Done | |
|
|
Tiago Ribeiro | Done |
For some reason the dates run over the weekend - hope Tiago doesn't mind.
These dates are in the past and therefore we can't move them in P6 so they really don't matter (to the work currently at hand).