Uploaded image for project: 'Data Management'
  1. Data Management
  2. DM-18449

MainTel Calibration System Integration Tests in Tucson

    XMLWordPrintable

    Details

    • Epic Name:
      MainTel Calibration System Integration Tests in Tucson
    • Story Points:
      30
    • WBS:
      1.04C.08.01 (Calibration)
    • Team:
      Telescope and Site

      Description

      Location:

      • Tucson

      Purpose:

      • MainTel Calibration System Integration Tests

      Required Components:

      • TunableLaser
      • FiberSpectrograph
      • Electrometer
      • CBP
      • LinearStage

      Resources Required:

      • Integration & Test Environment
      • SAL
      • EFD
      • Calibration Scripts

        Attachments

          Issue Links

          Stories in Epic (Custom Issue Matrix)

          Key Summary Story Points Assignee Status
           
          DM-21310

          Update LinearStage to salobj 4

          2 Eric Coughlin Done

            Activity

            Hide
            aclements Andy Clements added a comment -

            Adding guestimated dates via Patrick.

            Show
            aclements Andy Clements added a comment - Adding guestimated dates via Patrick.
            Hide
            aclements Andy Clements added a comment -

            Patrick Ingraham - should we close this epic?  Eric is no longer charging against this account number...  We have another epic for TSSW (DM-20181) that will capture the on-going work for calibration.

            Show
            aclements Andy Clements added a comment - Patrick Ingraham - should we close this epic?  Eric is no longer charging against this account number...  We have another epic for TSSW ( DM-20181 ) that will capture the on-going work for calibration.
            Hide
            pingraham Patrick Ingraham added a comment -

            Sure.

            Show
            pingraham Patrick Ingraham added a comment - Sure.
            Hide
            aclements Andy Clements added a comment -

            no longer charging against this account number...  We have another epic for TSSW (DM-20181) that will capture the on-going work for calibration.

            Show
            aclements Andy Clements added a comment - no longer charging against this account number...  We have another epic for TSSW ( DM-20181 ) that will capture the on-going work for calibration.
            Hide
            pingraham Patrick Ingraham added a comment -

            work completed, remaining work, to be carried out at a later date, is captured in DM-20181

            Show
            pingraham Patrick Ingraham added a comment - work completed, remaining work, to be carried out at a later date, is captured in DM-20181

              People

              Assignee:
              ecoughlin Eric Coughlin
              Reporter:
              jbuffill James Buffill [X] (Inactive)
              Reviewers:
              Patrick Ingraham
              Watchers:
              Andy Clements, James Buffill [X] (Inactive), Patrick Ingraham, Tiago Ribeiro
              Votes:
              0 Vote for this issue
              Watchers:
              4 Start watching this issue

                Dates

                Created:
                Updated:
                Resolved:
                Start date:
                End date:

                  Jenkins

                  No builds found.