Support M2 mirror coating chamber activity

    Details

      Description

      Milestone Epic Level 2

       

        Attachments

          Activity

          Hide
          aclements Andy Clements added a comment -

          M2 mirror coating complete.  Time to review milestone.

          Show
          aclements Andy Clements added a comment - M2 mirror coating complete.  Time to review milestone.
          Hide
          aclements Andy Clements added a comment -

          M2 mirror coating is complete.   Andrew Heyer participated in the coating.

          Show
          aclements Andy Clements added a comment - M2 mirror coating is complete.   Andrew Heyer participated in the coating.

            People

            • Assignee:
              aheyer Andrew Heyer
              Reporter:
              jbuffill James Buffill [X] (Inactive)
              Watchers:
              Andrew Heyer, Andy Clements, Christopher Contaxis [X] (Inactive), James Buffill [X] (Inactive)