    Details

    • Milestone Level:
      3
    • WBS:
      1.04C.15.2 (Main Telescope)
    • Team:
      Telescope and Site

      Description

      This milestone shows that the Camera Hex/Rot, Camera Cable Wrap (CCW) from the TMA & and the Camera Cart integration testing has been successfully completed.

        Attachments

          Activity

          Hide
          aclements Andy Clements added a comment -

          Hi Sandrine - can you please review this milestone and complete the review if we have achieved it?  Thanks.

          Show
          aclements Andy Clements added a comment - Hi Sandrine - can you please review this milestone and complete the review if we have achieved it?  Thanks.
          Hide
          sthomas Sandrine Thomas added a comment -

          Andy Clements do we have another milestone for the work that will be done in March?

          Show
          sthomas Sandrine Thomas added a comment - Andy Clements do we have another milestone for the work that will be done in March?
          Hide
          scallahan Shawn Callahan added a comment -

          Excellent work coordinating Tekniker's visit to the summit and for the transfer of information to the Rubin Observatory staff.

           

          Clearly the information garnered will be used in determining future work required.

           

          Thanks everyone,

          Shawn

          Show
          scallahan Shawn Callahan added a comment - Excellent work coordinating Tekniker's visit to the summit and for the transfer of information to the Rubin Observatory staff.   Clearly the information garnered will be used in determining future work required.   Thanks everyone, Shawn
          Hide
          scallahan Shawn Callahan added a comment -

          Thanks for the excellent work in accomodating Tekniker's visit to the summit and for the successful transfer of information to the Rubin Observatory.

          Show
          scallahan Shawn Callahan added a comment - Thanks for the excellent work in accomodating Tekniker's visit to the summit and for the successful transfer of information to the Rubin Observatory.

            People

            Assignee:
            aheyer Andrew Heyer [X] (Inactive)
            Reporter:
            jbuffill James Buffill [X] (Inactive)
            Watchers:
            Andrew Heyer [X] (Inactive), Andy Clements, James Buffill [X] (Inactive), Sandrine Thomas, Shawn Callahan
            Votes:
            0 Vote for this issue
            Watchers:
            5 Start watching this issue

              Dates

              Due:
              Created:
              Updated:
              Resolved:

                Jenkins

                No builds found.