Uploaded image for project: 'Data Management'
  1. Data Management
  2. DM-20404

Build Initial BPS Job Activator

    Details

    • Epic Name:
      Build Initial BPS Job Activator
    • Story Points:
      24
    • WBS:
      02C.07.08
    • Team:
      Data Facility
    • Cycle:
      Fall 2019

      Description

      Work includes separating science output from initial operations output, working with Sys. Admins to reuse current activator code. The scope of this epic is looking at the basic features, and does not include advanced features like clustering. At the completion of this epic we will test that operator reruns the latest Pegasus ci_hsc test that was successful (i.e., no debugging new pipeline steps).

        Attachments

          Issue Links

          Stories in Epic (Custom Issue Matrix)

            Activity

            There are no comments yet on this issue.

              People

              • Assignee:
                mgower Michelle Gower
                Reporter:
                mgower Michelle Gower
                Watchers:
                Joel Plutchak (Inactive)
              • Votes:
                0 Vote for this issue
                Watchers:
                1 Start watching this issue

                Dates

                • Created:
                  Updated:
                  Start date:
                  End date: