  1. Data Management
  2. DM-21232

Support for Hexapod/Rotator System Ready for Integration in Phase 2

    XMLWordPrintable

    Details

    • Epic Name:
      Support for M2 Hexapod System Ready for Integration in Phase 2
    • Story Points:
      13
    • WBS:
      1.04C.15.2 (Main Telescope)
    • Team:
      Telescope and Site

      Description

      Continued changes and support for M2 Hexapod System to be ready for Integration

      Corresponding P6 Activity:

      T&SC-140403-1300 - M2 Hexapod System Ready for Integration

        Attachments

        Stories in Epic (Custom Issue Matrix)

          Activity

          Hide
          ttsai Te-Wei Tsai added a comment -

          The epic is considered done. The updated middleware code worked well in SLAC. The inconsistency between code and document LTS-160 is recorded on the confluence page.

          Show
          ttsai Te-Wei Tsai added a comment - The epic is considered done. The updated middleware code worked well in SLAC. The inconsistency between code and document LTS-160 is recorded on the confluence page.
          Hide
          aclements Andy Clements added a comment -

          Test successfully completed at SLAC for the Rotator.  Epic complete.

          Show
          aclements Andy Clements added a comment - Test successfully completed at SLAC for the Rotator.  Epic complete.

            People

            Assignee:
            ttsai Te-Wei Tsai
            Reporter:
            aclements Andy Clements
            Reviewers:
            Andy Clements
            Watchers:
            Andy Clements, Bo Xin [X] (Inactive), Sandrine Thomas, Te-Wei Tsai
            Votes:
            0 Vote for this issue
            Watchers:
            4 Start watching this issue

              Dates

              Due:
              Created:
              Updated:
              Resolved:
              Start date:
              End date:

                Jenkins

                No builds found.