TMA Work Phase 2

    XMLWordPrintable

Details

    • Epic
    • Status: Done
    • Resolution: Done
    • None
    • ts_main_telescope
    • TMA Work Phase 2
    • 20
    • 1.04C.15.2 (Main Telescope)
    • Telescope and Site

    Description

      TMA Training & Review of Labview-based vendor software in Tucson & Spain.

      Also any on-going work & support regarding the TMA.

      This is a continuation of DM-19848

      Attachments

        Activity

          Hi Shawn, We have filled up this epic with work for the TMA.  Please review this epic and note that the work listed is complete.  If so, please click the "Review Complete" button at the top.  We do this to track all the work that TSSW does.  Thanks.

          aclements Andy Clements added a comment - Hi Shawn, We have filled up this epic with work for the TMA.  Please review this epic and note that the work listed is complete.  If so, please click the "Review Complete" button at the top.  We do this to track all the work that TSSW does.  Thanks.

          scallahan signed off on the milestone associated with this epic, therefore this epic is complete.  Review Complete.

          aclements Andy Clements added a comment - scallahan signed off on the milestone associated with this epic, therefore this epic is complete.  Review Complete.

          People

            aheyer Andrew Heyer [X] (Inactive)
            aclements Andy Clements
            Shawn Callahan
            Andy Clements, Sandrine Thomas, Shawn Callahan
            Votes:
            0 Vote for this issue
            Watchers:
            3 Start watching this issue

            Dates

              Created:
              Updated:
              Resolved:

              Jenkins

                No builds found.