          ecoughlin Eric Coughlin added a comment - - edited

          Last set of cycle 1, 2 and 3 tests done to best of ability.

          Duration test ran for 8 hours and completed with no failures or fault states.

          Show
          ecoughlin Eric Coughlin added a comment - - edited Last set of cycle 1, 2 and 3 tests done to best of ability. Duration test ran for 8 hours and completed with no failures or fault states.
          Hide
          rbovill Rob Bovill added a comment -

          The M1M3 Cell functional testing in Chile is complete.

          Show
          rbovill Rob Bovill added a comment - The M1M3 Cell functional testing in Chile is complete.

            People

            Assignee:
            ecoughlin Eric Coughlin
            Reporter:
            ecoughlin Eric Coughlin
            Reviewers:
            Rob Bovill
            Watchers:
            Andy Clements, Eric Coughlin, Felipe Daruich, Patrick Ingraham, Rob Bovill, Tiago Ribeiro
            Votes:
            0 Vote for this issue
            Watchers:
            6 Start watching this issue

              Dates

              Created:
              Updated:
              Resolved:

                Jenkins

                No builds found.