Testing M1M3 Cell phase 5 part 2

    XMLWordPrintable

Details

    • Story
    • Status: Done
    • Resolution: Done
    • None
    • ts_aos

    Attachments

      Issue Links

        Activity

          ecoughlin Eric Coughlin added a comment - - edited

          Last set of cycle 1, 2 and 3 tests done to best of ability.

          Duration test ran for 8 hours and completed with no failures or fault states.

          ecoughlin Eric Coughlin added a comment - - edited Last set of cycle 1, 2 and 3 tests done to best of ability. Duration test ran for 8 hours and completed with no failures or fault states.
          rbovill Rob Bovill added a comment -

          The M1M3 Cell functional testing in Chile is complete.

          rbovill Rob Bovill added a comment - The M1M3 Cell functional testing in Chile is complete.

          People

            ecoughlin Eric Coughlin
            ecoughlin Eric Coughlin
            Rob Bovill
            Andy Clements, Eric Coughlin, Felipe Daruich, Patrick Ingraham (Inactive), Rob Bovill, Tiago Ribeiro
            Votes:
            0 Vote for this issue
            Watchers:
            6 Start watching this issue

            Dates

              Created:
              Updated:
              Resolved:

              Jenkins

                No builds found.