Any assembly/testing needed at the summit for the Camera Hex/Rot to be ready for the individual functional testing as well as the Camera Rot/CCW/Camera Cart integration testing. Will be working in tandem with IT (IT-1145) in regards to this process.
Will probably need switches and/or UPS from IT to complete this task.
Spent a couple of days organizing, setting up and connecting the Camera Rotator and Hexapod cabinets, got electrical UPS power going to them, got the private rotator network started and the connected the Rotator Management Server to the public network and got Te-Wei access to said server. Reviewed the entire thing with Eric and passed it off to him