Description
After the last run with the AT there where some bug fixes and configuration changes needed. Most of the work was done on DM-22531. This task is to clean up all the components that where deployed with non-tagged repositories and also to switch up the kafka producers to publish data to the new EFD deployment.
Unfortunately, I was not able to perform the clean up that I wanted to. Instead I had to deal with the updates needed for the LATISS work done during that week. This is going to be replaced by xml 4.6 during this sprint.
PR to the compose-ops.
https://github.com/lsst-it/docker-compose-ops/pull/12