Details
-
Type:
Epic
-
Status: Done
-
Resolution: Done
-
Fix Version/s: None
-
Component/s: ts_main_telescope
-
Labels:
-
Epic Name:M2 Upgrades Phase 3
-
Story Points:30
-
WBS:1.04C.15.2 (Main Telescope)
-
Team:Telescope and Site
Description
This epic contains the stories for the upgrades in software on the M2 system. This epic is phase 3 for:
M2 Functionality Check with CSC Controller + SAL @ the Summit:
- Install the latest SAL version and rerun functionality tests
This Epic will also update the LabVIEW version to LabVIEW 2018 SP1, and xml with description and unit.
This Epic will correspond to the following P6 Activity:
- T&SC -14040404-1060 (Verify M2 Functionality)
Attachments
Key | Summary | Story Points | Assignee | Status | |
---|---|---|---|---|---|
|
|
3 | Te-Wei Tsai | Done | |
|
|
0 | Te-Wei Tsai | Done | |
|
|
4 | Te-Wei Tsai | Done | |
|
|
3 | Te-Wei Tsai | Done | |
|
|
0 | Te-Wei Tsai | Done | |
|
|
3 | Tiago Ribeiro | Done | |
|
|
3 | Te-Wei Tsai | Done | |
|
|
2 | Te-Wei Tsai | Done | |
|
|
2 | Te-Wei Tsai | Done | |
|
|
Check the SAL Event and Telemetry in M2 Control System in Phase 2 |
1 | Te-Wei Tsai | Done |
|
|
Check the SAL Event and Telemetry in M2 Control System Phase 1 |
3 | Te-Wei Tsai | Done |
|
|
3 | Te-Wei Tsai | Done | |
|
|
1 | Te-Wei Tsai | Done | |
|
|
Create the M2 GUI/DDS Startup Procedure in Jira Test Manager |
1 | Te-Wei Tsai | Done |
|
|
1 | Te-Wei Tsai | Done |
Hi Bo, looks like this epic is out of story points, work on M2 will continue in
DM-26164. Please review so we can close this out. Thanks.