Assist with debugging M1M3 system startup for SAL4 integration tests

    XMLWordPrintable

    Details

      Description

      Assist with any debug and preparation work required to get the M1M3 control
      system to the state where it is ready to install the SAL 4 compatible software
      and execute tests

        Attachments

          Activity

          Hide
          dmills Dave Mills added a comment -

          Done in last sprint

          Show
          dmills Dave Mills added a comment - Done in last sprint
          Hide
          aclements Andy Clements added a comment -

          Dave worked on the summit to bring the M1M3 into the SAL 4.0 realm.  Work has been completed.  Review Complete.

          Show
          aclements Andy Clements added a comment - Dave worked on the summit to bring the M1M3 into the SAL 4.0 realm.  Work has been completed.  Review Complete.

            People

            Assignee:
            dmills Dave Mills
            Reporter:
            dmills Dave Mills
            Reviewers:
            Andy Clements
            Watchers:
            Andy Clements, Dave Mills
            Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

              Dates

              Created:
              Updated:
              Resolved: