Description
Another week on the summit to test the hex/rot now that on Monday (while I was on vacation) IT reset the switches and so the network needed to be tested again. The largest activities which I supported during this was.
- Re-do the bump test on the M2
- Continue testing the rotator according to an LVV document by Systems Engineering https://jira.lsstcorp.org/secure/Tests.jspa#/testPlayer/testExecution/LVV-E1140
- Verify that data from all tests was reaching the EFD
- Learn from Tiago how to work on the JupiterLab which runs on the control network to run a Remote to control a CSC through SAL. We used this to test the Rotator via SAL
Andrew supported the summit activity and verified the functionality of M2 and rotator. The Jupyter notebook was used to test the SAL and rotator. Great job done!