Uploaded image for project: 'Data Management'
  1. Data Management
  2. DM-27545

TMA Automatic Testing System (ATS) Part 1

    XMLWordPrintable

    Details

    • Type: Epic
    • Status: Done
    • Resolution: Done
    • Fix Version/s: None
    • Component/s: ts_main_telescope
    • Labels:
    • Epic Name:
      TMA Automatic Testing System (ATS) Part 1
    • Story Points:
      20
    • WBS:
      1.04C.15.2 (Main Telescope)
    • Team:
      Telescope and Site
    • Epic Priority:
      4

      Description

      On-going work of the Chilean implementation of the ATS. Includes procurement of all necessary hardware - The PILZ req, which is already been created and seems to be making good progress. Req #0000002760 - 1x cRIO, and 2x chassis so that they can be rack mounted. I am waiting for NI to give me a quote after I asked them to modify the quote to only have 1 cRIO instead of 2. - The EIB, Tekniker has a spare one that they are giving us. I am currently working on getting this shipped here. - A server to replace the PXI desktops since IT does not like to have non-server grade hardware in the server room.

        Attachments

          Issue Links

            Activity

            No builds found.
            aclements Andy Clements created issue -
            aclements Andy Clements made changes -
            Field Original Value New Value
            Link This issue has to be done after DM-25842 [ DM-25842 ]
            aclements Andy Clements made changes -
            Link This issue has to be done before DM-27549 [ DM-27549 ]
            aclements Andy Clements made changes -
            Epic Child DM-27552 [ 441692 ]
            aclements Andy Clements made changes -
            Epic Child DM-27759 [ 442203 ]
            aclements Andy Clements made changes -
            Status To Do [ 10001 ] In Progress [ 3 ]
            aclements Andy Clements made changes -
            Remote Link This issue links to "Page (Confluence)" [ 27801 ]
            aclements Andy Clements made changes -
            Epic Child DM-29010 [ 455512 ]
            aclements Andy Clements made changes -
            End date 01/Feb/21 01/Jun/21
            aclements Andy Clements made changes -
            Epic Priority 4
            aclements Andy Clements made changes -
            Epic Child DM-29553 [ 466312 ]
            aclements Andy Clements made changes -
            Epic Child DM-28974 [ 455004 ]
            aclements Andy Clements made changes -
            Assignee Andrew Heyer [X] [ aheyer ] Eric Coughlin [ ecoughlin ]
            aclements Andy Clements made changes -
            Watchers Andy Clements, Russell Owen [ Andy Clements, Russell Owen ] Andy Clements, Dave Mills, Russell Owen [ Andy Clements, Dave Mills, Russell Owen ]
            aclements Andy Clements made changes -
            Epic Child DM-30001 [ 482681 ]
            aclements Andy Clements made changes -
            Epic Child DM-30347 [ 502045 ]
            aclements Andy Clements made changes -
            Epic Child DM-30834 [ 537595 ]
            aclements Andy Clements made changes -
            Epic Child DM-31588 [ 672812 ]
            aclements Andy Clements made changes -
            Epic Child DM-31411 [ 637750 ]
            aclements Andy Clements made changes -
            Epic Child DM-31338 [ 614188 ]
            aclements Andy Clements made changes -
            Epic Child DM-31142 [ 583182 ]
            aclements Andy Clements made changes -
            Epic Child DM-31008 [ 558246 ]
            aclements Andy Clements made changes -
            Epic Child DM-30832 [ 536881 ]
            aclements Andy Clements made changes -
            Epic Child DM-30681 [ 519665 ]
            aclements Andy Clements made changes -
            Epic Child DM-30001 [ 482681 ]
            Hide
            aclements Andy Clements added a comment -

            Hi Sandrine - As per the already reviewed milestone, all the hardware has been obtained, racked and wired up in the base server room.   We have completed all the story points for this task and it is ready for review.  Continued work on the ATS will go on with DM-27549.  Can you please review it, and let me know if you have any questions.  Thanks!

            Show
            aclements Andy Clements added a comment - Hi Sandrine - As per the already reviewed milestone, all the hardware has been obtained, racked and wired up in the base server room.   We have completed all the story points for this task and it is ready for review.  Continued work on the ATS will go on with DM-27549 .  Can you please review it, and let me know if you have any questions.  Thanks!
            aclements Andy Clements made changes -
            Status In Progress [ 3 ] In Review [ 10004 ]
            Hide
            sthomas Sandrine Thomas added a comment -

            It looks good to me and the remaining required work will continue in DM-27549

             

            Show
            sthomas Sandrine Thomas added a comment - It looks good to me and the remaining required work will continue in DM-27549 .   
            sthomas Sandrine Thomas made changes -
            Status In Review [ 10004 ] Reviewed [ 10101 ]
            aclements Andy Clements made changes -
            Resolution Done [ 10000 ]
            Status Reviewed [ 10101 ] Done [ 10002 ]
            dmills Dave Mills made changes -
            Epic Child DM-32347 [ 822862 ]

              People

              Assignee:
              ecoughlin Eric Coughlin
              Reporter:
              aclements Andy Clements
              Reviewers:
              Sandrine Thomas
              Watchers:
              Andy Clements, Dave Mills, Russell Owen, Sandrine Thomas
              Votes:
              0 Vote for this issue
              Watchers:
              4 Start watching this issue

                Dates

                Due:
                Created:
                Updated:
                Resolved:
                Start date:
                End date:

                  Jenkins

                  No builds found.