Details
-
Type:
Epic
-
Status: Done
-
Resolution: Done
-
Fix Version/s: None
-
Component/s: ts_main_telescope
-
Labels:
-
Epic Name:TMA Automatic Testing System (ATS) Part 2
-
Story Points:40
-
WBS:1.04C.15.2 (Main Telescope)
-
Team:Telescope and Site
-
Epic Priority:7
Description
Completion of the Chilean implementation of the ATS. - A few of the elements within the ATS have been "dockerized", what can be put in Docker or virtual machines is done. - What is left to do is complete writing of the Deployable Platform tests I estimate another sprint to have this completed. - In parallel to the tests I am also connecting the hardware which I do have to run the ATS. That is the ATS minus the EIB, the cRIOS, and speedgoat in my office. I want to complete this test before I leave. - Once I return in January I want to then include the speedgoat, cRIO's, and EIB to have the full ATS running within the Simulation Cluster.
Attachments
Issue Links
Key | Summary | Story Points | Assignee | Status | |
---|---|---|---|---|---|
|
Dave Mills | Done | |||
|
1 | Dave Mills | Done | ||
|
5 | Eric Coughlin | Done | ||
|
3 | Dave Mills | Done | ||
|
1 | Dave Mills | Done | ||
|
8 | Eric Coughlin | Done | ||
|
Review the Latest Trajectory and Deployment Documents of TMA |
1 | Te-Wei Tsai | Done | |
|
1 | Dave Mills | Done | ||
|
3 | Dave Mills | Done | ||
|
2 | Dave Mills | Done | ||
|
7 | Eric Coughlin | Done | ||
|
8 | Eric Coughlin | Done |
Activity
Epic Child | DM-27554 [ 441694 ] |
Remote Link | This issue links to "Page (Confluence)" [ 27785 ] |
Start date | 29/Jan/21 | 01/Jun/21 |
End date | 30/Apr/21 | 30/Aug/21 |
End date | 30/Aug/21 | 31/Aug/21 |
Epic Priority | 7 |
Assignee | Andrew Heyer [X] [ aheyer ] | Eric Coughlin [ ecoughlin ] |
Watchers | Andy Clements, Russell Owen [ Andy Clements, Russell Owen ] | Andy Clements, Dave Mills, Rob Bovill, Russell Owen [ Andy Clements, Dave Mills, Rob Bovill, Russell Owen ] |
Status | To Do [ 10001 ] | In Progress [ 3 ] |
Epic Child | DM-30001 [ 482681 ] |
Epic Child |
|
Epic Child |
|
Epic Child |
|
Epic Child |
|
Epic Child |
|
Epic Child |
|
Epic Child |
|
Epic Child |
|
Epic Child |
|
Epic Child |
|
Epic Child |
|
Epic Child |
|
Epic Child |
|
Epic Child | DM-30001 [ 482681 ] |
Epic Child | DM-27554 [ 441694 ] |
Status | In Progress [ 3 ] | In Review [ 10004 ] |
Epic Child |
|
Epic Child |
|
Epic Child |
|
Epic Child |
|
Epic Child |
|
Status | In Review [ 10004 ] | Reviewed [ 10101 ] |
Resolution | Done [ 10000 ] | |
Status | Reviewed [ 10101 ] | Done [ 10002 ] |
Hi Sandrine - this epic has completed its story points. Work is almost complete, and will be continued on epic
DM-27717. The milestone is also not complete and has been moved over to that epic. Please review this epic at your earliest convenience. Thanks!