Revise early integration milestones, LCR-323 and beyond

    XMLWordPrintable

    Details

    • Epic Name:
      Revise early integration milestones
    • Story Points:
      6
    • WBS:
      02C.02.02
    • Team:
      Architecture
    • Cycle:
      Winter 2016

      Description

      Revise the list of early integration milestones with OCS, TCS, CCS, and DAQ to form a coherent plan. Coordinate with NCSA and other interested parties in DM.

        Attachments

        Stories in Epic (Custom Issue Matrix)

        Key Summary Story Points Assignee Status
         
        DM-3891

        Review LCR-323 proposal for integration milestones

        4 Gregory Dubois-Felsmann Done

          Activity

          Hide
          gpdf Gregory Dubois-Felsmann added a comment -

          Fully implemented in February 2016 PMCS baseline.

          Show
          gpdf Gregory Dubois-Felsmann added a comment - Fully implemented in February 2016 PMCS baseline.
          Hide
          gpdf Gregory Dubois-Felsmann added a comment -

          A second round of DAQ-related work on the integration schedule will still be needed.

          Show
          gpdf Gregory Dubois-Felsmann added a comment - A second round of DAQ-related work on the integration schedule will still be needed.

            People

            Assignee:
            ktl Kian-Tat Lim
            Reporter:
            gpdf Gregory Dubois-Felsmann
            Watchers:
            Gregory Dubois-Felsmann
            Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

              Dates

              Created:
              Updated:
              Resolved:

                Jenkins

                No builds found.