Revise LSE-140 to account for recent changes to calibration instrumentation

    Details

    • Epic Name:
      LSE-140 update early 2016
    • Story Points:
      5
    • WBS:
      02C.02
    • Team:
      Architecture
    • Cycle:
      Winter 2016

      Description

      Produce a revision of LSE-140, the DM - to - auxiliary instrumentation ICD, taking into account recent changes to the calibration instrumentation.

        Attachments

          Issue Links

          Stories in Epic (Custom Issue Matrix)

            Activity

            Hide
            gpdf Gregory Dubois-Felsmann added a comment -

            Work is beginning on LSE-140 Phase 3 toward the DMTC-0100-4500 milestone.

            Show
            gpdf Gregory Dubois-Felsmann added a comment - Work is beginning on LSE-140 Phase 3 toward the DMTC-0100-4500 milestone.
            Hide
            gpdf Gregory Dubois-Felsmann added a comment -

            This is being entered as Winter 2016 work because the stretch goal of the effort is to get a non-controversial change request through the mid-March CCB meeting. If this falls back to the April CCB I'll work out with Jacek Becla how to represent the shift of work to X16.

            Show
            gpdf Gregory Dubois-Felsmann added a comment - This is being entered as Winter 2016 work because the stretch goal of the effort is to get a non-controversial change request through the mid-March CCB meeting. If this falls back to the April CCB I'll work out with Jacek Becla how to represent the shift of work to X16.
            Hide
            gpdf Gregory Dubois-Felsmann added a comment -

            The 20 April 2016 CCB meeting recommended the update of LSE-140 for approval.

            Show
            gpdf Gregory Dubois-Felsmann added a comment - The 20 April 2016 CCB meeting recommended the update of LSE-140 for approval.

              People

              • Assignee:
                gpdf Gregory Dubois-Felsmann
                Reporter:
                gpdf Gregory Dubois-Felsmann
                Watchers:
                Gregory Dubois-Felsmann, Jacek Becla, Patrick Ingraham
              • Votes:
                0 Vote for this issue
                Watchers:
                3 Start watching this issue

                Dates

                • Created:
                  Updated:
                  Resolved:

                  Summary Panel

                    Time Tracking

                    Estimated:
                    Original Estimate - 2 days, 4 hours
                    2d 4h
                    Remaining:
                    Remaining Estimate - 2 days, 4 hours
                    2d 4h
                    Logged:
                    Time Spent - Not Specified