Description
We have updated the operations costs for the Rubin Observatory Networks, in the course of revising the Operations Proposal. The Operations Proposal references LDM-142 and so they need to be kept in synch.
Construction/commissioning costs have not changed, except that in LDM-142 there was a $320k one-time cost and $30k yearly recurring costs for NCSA Archive Network (Chicago - Champaign) WBS 02C.07.04. These appear to have already been added into operations costs in the original proposal. Wil O'Mullane and Bob Blum need to understand what the exact situation is.
Revised spreadsheet is attached to this RFC.
Yes, he was concerned that it implied we were violating the "color of money" restriction between MREFC and Ops.