Details
-
Milestone
-
Status: Unplanned
-
Major
-
Resolution: Unresolved
-
None
-
1.04C.11.12
-
Empty show more show less
Description
Corresponds to activity ID T&SC-6800-0045 in the calibration WBS.
This is the control system that will drive the Auxiliary Telescope Dome. Note that the dome controller is currently slated to be provided by ACE. Details of this are still being flushed out.
Released version of dome control software and controller will be available in Tucson.
EndDate will be updated when a delivery date is received.
Attachments
Activity
Patrick Ingraham (Inactive)
created issue -
Srinivasan Chandrasekharan [X] (Inactive)
made changes -
Field | Original Value | New Value |
---|---|---|
End date | 17/Oct/17 | 17/Oct/17 |
Start date | 07/Apr/16 |
Srinivasan Chandrasekharan [X] (Inactive)
made changes -
Start date | 07/Apr/16 | 17/Oct/17 |
Paul Lotz [X] (Inactive)
made changes -
Component/s | TCS Auxiliary Telescope [ 12520 ] | |
Component/s | TCS Auxiliary Instruments [ 12522 ] | |
End date | 17/Oct/17 | 17/Oct/17 |
Start date | 17/Oct/17 | 17/Oct/17 |
Srinivasan Chandrasekharan [X] (Inactive)
made changes -
Srinivasan Chandrasekharan [X] (Inactive)
made changes -
WBS | 1.04C.11.12 |
Srinivasan Chandrasekharan [X] (Inactive)
made changes -
Baseline end date | 17/Oct/17 | |
Baseline start date | 17/Oct/17 |
Srinivasan Chandrasekharan [X] (Inactive)
made changes -
Summary | Auxiliary Telescope Dome Control System | AT Dome Control System |
Harini Sundararaman [X] (Inactive)
made changes -
Baseline end date | 17/Oct/17 | 17/Oct/17 |
Harini Sundararaman [X] (Inactive)
made changes -
Summary | AT Dome Control System | AT Dome Control System(ACE) |
Harini Sundararaman [X] (Inactive)
made changes -
Harini Sundararaman [X] (Inactive)
made changes -
Harini Sundararaman [X] (Inactive)
made changes -
Harini Sundararaman [X] (Inactive)
made changes -
Harini Sundararaman [X] (Inactive)
made changes -
Paul Lotz [X] (Inactive)
made changes -
Paul Lotz [X] (Inactive)
made changes -
Paul Lotz [X] (Inactive)
made changes -
Link | This issue has to be done before TSS-1334 [ TSS-1334 ] |
Paul Lotz [X] (Inactive)
made changes -
Link | This issue has to be done before TSS-1334 [ TSS-1334 ] |
Paul Lotz [X] (Inactive)
made changes -
Link | This issue has to be done before TSS-1087 [ TSS-1087 ] |
Harini Sundararaman [X] (Inactive)
made changes -
Link | This issue has to be done before TSS-1087 [ TSS-1087 ] |
Harini Sundararaman [X] (Inactive)
made changes -
Link | This issue has to be done before TSS-1097 [ TSS-1097 ] |
Harini Sundararaman [X] (Inactive)
made changes -
Description |
Corresponds to activity ID T&SC-6800-0045 in the calibration WBS.
This is the control system that will drive the Auxiliary Telescope Dome. Note that the dome controller is currently slated to be provided by ACE. Details of this are still being flushed out. EndDate will be updated when a delivery date is received. |
Corresponds to activity ID T&SC-6800-0045 in the calibration WBS.
This is the control system that will drive the Auxiliary Telescope Dome. Note that the dome controller is currently slated to be provided by ACE. Details of this are still being flushed out. Released version of dome control software and controller will be available in Tucson. EndDate will be updated when a delivery date is received. |
Harini Sundararaman [X] (Inactive)
made changes -
End date | 17/Oct/17 | 05/Oct/17 |
Start date | 17/Oct/17 | 05/Oct/17 |
Harini Sundararaman [X] (Inactive)
made changes -
End date | 05/Oct/17 | 06/Feb/18 |
Start date | 05/Oct/17 | 06/Feb/18 |
Harini Sundararaman [X] (Inactive)
made changes -
End date | 06/Feb/18 | 17/Oct/17 |
Start date | 06/Feb/18 | 17/Oct/17 |
Harini Sundararaman [X] (Inactive)
made changes -
Start date | 17/Oct/17 | 16/Oct/17 |
Harini Sundararaman [X] (Inactive)
made changes -
End date | 17/Oct/17 | 16/Oct/17 |
Harini Sundararaman [X] (Inactive)
made changes -
End date | 16/Oct/17 | 17/Oct/17 |
Start date | 16/Oct/17 | 17/Oct/17 |