Details

    • Milestone
    • Status: Unplanned
    • Major
    • Resolution: Unresolved
    • None

    Description

      This activity is tied to the start date of Activity ID T&SC-6800-0154 in the calibration WBS.

      This is the start date for Tucson TCS testing of the auxiliary telescope. The telescope will be ready to hand off to the T&S software team at this time.

      Attachments

        Activity

          pingraham Patrick Ingraham (Inactive) created issue -
          pingraham Patrick Ingraham (Inactive) made changes -
          Field Original Value New Value
          Issue Type Meta-epic [ 10202 ] Milestone [ 10201 ]
          schandra Srinivasan Chandrasekharan [X] (Inactive) made changes -
          End date 17/Jan/17 17/Jan/17
          Start date 08/Apr/16
          schandra Srinivasan Chandrasekharan [X] (Inactive) made changes -
          Start date 08/Apr/16 17/Jan/17
          plotz Paul Lotz [X] (Inactive) made changes -
          End date 17/Jan/17 17/Jan/17
          Start date 17/Jan/17 17/Jan/17
          Description This activity is tied to the start date of Activity ID T&SC-6800-0154 in the calibratoin WBS.

          This is the start date for Tucson TCS testing of the auxiliary telescope. The telescope will be ready to hand off to the T&S software team at this time.

          Date is TBR.
          This activity is tied to the start date of Activity ID T&SC-6800-0154 in the calibration WBS.

          This is the start date for Tucson TCS testing of the auxiliary telescope. The telescope will be ready to hand off to the T&S software team at this time.

          Date is TBR.
          schandra Srinivasan Chandrasekharan [X] (Inactive) made changes -
          Link This issue has to be finished together with TSSPP-155 [ TSSPP-155 ]
          schandra Srinivasan Chandrasekharan [X] (Inactive) made changes -
          WBS 1.04C.11.12
          schandra Srinivasan Chandrasekharan [X] (Inactive) made changes -
          Baseline end date 17/Jan/17
          Baseline start date 17/Jan/17
          schandra Srinivasan Chandrasekharan [X] (Inactive) made changes -
          Summary Auxiliary Telescope TCS Tucson Testing Start AT Tucson Testing Start
          pingraham Patrick Ingraham (Inactive) made changes -
          End date 17/Jan/17 12/Apr/17
          Start date 17/Jan/17 12/Apr/17
          Description This activity is tied to the start date of Activity ID T&SC-6800-0154 in the calibration WBS.

          This is the start date for Tucson TCS testing of the auxiliary telescope. The telescope will be ready to hand off to the T&S software team at this time.

          Date is TBR.
          This activity is tied to the start date of Activity ID T&SC-6800-0154 in the calibration WBS.

          This is the start date for Tucson TCS testing of the auxiliary telescope. The telescope will be ready to hand off to the T&S software team at this time.
          plotz Paul Lotz [X] (Inactive) made changes -
          Baseline end date 17/Jan/17 12/Apr/17
          Baseline start date 17/Jan/17 12/Apr/17
          plotz Paul Lotz [X] (Inactive) made changes -
          Link This issue has to be finished together with TSSPP-155 [ TSSPP-155 ]
          plotz Paul Lotz [X] (Inactive) made changes -
          Link This issue has to be done before TSSPP-155 [ TSSPP-155 ]
          plotz Paul Lotz [X] (Inactive) made changes -
          Link This issue has to be done before TSSPP-155 [ TSSPP-155 ]
          plotz Paul Lotz [X] (Inactive) made changes -
          Link This issue has to be done after TSSPP-155 [ TSSPP-155 ]
          plotz Paul Lotz [X] (Inactive) made changes -
          End date 12/Apr/17 24/May/17
          Start date 12/Apr/17 24/May/17
          plotz Paul Lotz [X] (Inactive) made changes -
          End date 24/May/17 16/May/17
          Start date 24/May/17 16/May/17
          plotz Paul Lotz [X] (Inactive) made changes -
          End date 16/May/17 24/May/17
          Start date 16/May/17 24/May/17
          plotz Paul Lotz [X] (Inactive) made changes -
          End date 24/May/17 16/May/17
          Start date 24/May/17 16/May/17
          plotz Paul Lotz [X] (Inactive) made changes -
          End date 16/May/17 02/May/17
          Start date 16/May/17 02/May/17
          plotz Paul Lotz [X] (Inactive) made changes -
          End date 02/May/17 11/Apr/17
          Start date 02/May/17 11/Apr/17
          plotz Paul Lotz [X] (Inactive) made changes -
          Start date 11/Apr/17 12/Apr/17
          plotz Paul Lotz [X] (Inactive) made changes -
          End date 11/Apr/17 12/Apr/17
          hsundararaman Harini Sundararaman [X] (Inactive) made changes -
          Baseline end date 12/Apr/17 12/Apr/17
          hsundararaman Harini Sundararaman [X] (Inactive) made changes -
          Link This issue has to be done after TSSPP-155 [ TSSPP-155 ]

          People

            plotz Paul Lotz [X] (Inactive)
            pingraham Patrick Ingraham (Inactive)
            Patrick Ingraham (Inactive)
            Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

            Dates

              Created:
              Updated: