1.04C.11.12
-
Empty show more show less
Description
This milestone is related to the start of activity ID T&SC-6800-1462 in the calibration WBS.
The signals the start of spectrograph integration in chile. At this point software to operate the spectrograph should be completed.
Attachments
Issue Links
- has to be finished together with
-
TSSPP-167 AT Spectograph integration
- Unplanned
Activity
Patrick Ingraham (Inactive)
created issue -
Paul Lotz [X] (Inactive)
made changes -
Field | Original Value | New Value |
---|---|---|
Start date | 29/Jul/18 |
Paul Lotz [X] (Inactive)
made changes -
End date | 29/Jul/18 | 30/Jul/18 |
Start date | 29/Jul/18 | 30/Jul/18 |
Srinivasan Chandrasekharan [X] (Inactive)
made changes -
Component/s | TCS Auxiliary Telescope [ 12520 ] | |
Component/s | TCS Auxiliary Instruments [ 12522 ] |
Srinivasan Chandrasekharan [X] (Inactive)
made changes -
Srinivasan Chandrasekharan [X] (Inactive)
made changes -
WBS | 1.04C.11.12 |
Srinivasan Chandrasekharan [X] (Inactive)
made changes -
Baseline end date | 30/Jul/18 | |
Baseline start date | 30/Jul/18 |
Srinivasan Chandrasekharan [X] (Inactive)
made changes -
Summary | AUX Tel Spectrograph Chile Integration | AT Spectrograph Chile Integration |
Harini Sundararaman [X] (Inactive)
made changes -
Baseline end date | 30/Jul/18 | 30/Jul/18 |
Paul Lotz [X] (Inactive)
made changes -
Paul Lotz [X] (Inactive)
made changes -
Paul Lotz [X] (Inactive)
made changes -
End date | 30/Jul/18 | 22/Aug/18 |
Start date | 30/Jul/18 | 22/Aug/18 |